A practical guide from Bristol Party Wall
The Party Wall etc. Act 1996 is designed to balance the rights of the person planning construction (the Building Owner) with the rights of their neighbour (the Adjoining Owner). It ensures that works near shared walls or boundaries are carried out safely, fairly, and transparently.
Understanding your rights and responsibilities under the Act helps projects proceed smoothly while protecting both properties from unnecessary risk or dispute. This guide explains what each side is entitled to, what obligations apply, and how the process works in practice.
1. Rights of the Building Owner
As the Building Owner, the Act gives you the legal right to:
- carry out building works covered by the Act, provided the correct notices are served
- access a neighbour’s property temporarily where required for the works and confirmed in a Party Wall Award
- excavate or build near a boundary, subject to appropriate safeguards
- cut into, alter, or tie into a shared wall where legally permitted
- appoint a surveyor, or request the use of an Agreed Surveyor where appropriate
- request a Schedule of Condition to protect against future damage claims
The Act is intended to allow development to proceed — not to prevent it — provided the correct procedure is followed.
2. Responsibilities of the Building Owner
With these rights come important responsibilities. A Building Owner must:
- serve valid statutory notices before works begin
- give adjoining owners sufficient time to respond
- allow for surveyor involvement if a dissent occurs
- pay surveyor fees where the works benefit them
- avoid starting notifiable works until a Party Wall Award is served
- make good any damage caused by the works
- comply fully with the terms of the Party Wall Award
Clear communication and proper documentation are key to maintaining good neighbourly relations.
3. Rights of the Adjoining Owner (Neighbour)
As an Adjoining Owner, you have the right to:
- receive formal notice before works start
- ask questions and request additional information
- consent to or dissent from the notice without blocking the project
- appoint your own surveyor, with reasonable fees normally paid by the Building Owner
- have a Schedule of Condition prepared to protect your property
- raise concerns if works are not carried out in accordance with the Award
- request further surveyor decisions if circumstances change during the works
Dissent does not indicate hostility — it simply ensures appropriate professional oversight and protection.
4. Responsibilities of the Adjoining Owner
An Adjoining Owner is expected to:
- respond to a notice within the 14-day period
- understand that failure to respond is treated as a dissent
- allow reasonable access for surveyors or contractors where confirmed by an Award
- raise concerns promptly and through the surveyor process rather than informally
- comply with Award provisions relating to access, inspections, or temporary works
The Act protects both parties, but only if each engages constructively with the process.
5. Why Surveyors Play a Neutral Role
Party Wall surveyors do not act as advocates for one side. Their role is to:
- administer the Act impartially
- protect both properties
- ensure works are carried out safely and lawfully
- assess damage claims objectively
- issue further or amended Awards where necessary
Using an experienced surveyor — or agreeing on a single Agreed Surveyor — often leads to a quicker, calmer, and more cost-effective process.
6. Damage, Repairs, and Making Good
If building works cause damage to an adjoining property:
- the Building Owner is responsible for repair or compensation
- the surveyor determines how repairs should be carried out
- costs may be recovered from contractors or insurers where appropriate
A Schedule of Condition is crucial here, as it provides an objective record of the property’s condition before works began.
7. Access Rights and Temporary Works
The Act allows access to neighbouring land where necessary for construction, inspection, or protection. However:
- access must be reasonable and properly notified
- suitable temporary protection (such as hoarding, scaffolding, or coverings) must be provided
- disruption should be kept to a minimum and managed professionally
Access cannot be assumed or demanded informally — it must be supported by a notice or Party Wall Award.
Summary
The Party Wall Act gives the Building Owner the right to carry out lawful construction, while ensuring adjoining owners are protected, informed, and professionally represented. By serving notices correctly, appointing surveyors where required, preparing a Schedule of Condition, and complying with the Award, both parties benefit from a clear, fair, and legally robust process.
Bristol Party Wall helps building owners and neighbours understand their rights and responsibilities, keeps communication clear, and supports projects through the Party Wall process with minimal conflict or risk.





